Taking Possession of Your Bengaluru Flat: The Snagging and Handover Checklist

A practical handover checklist for a new Bengaluru flat: the documents to receive, a room-by-room snag list, the area check, and what to do with the final payment.

DesiAcres Editorial · 19 November 2026 · Updated 19 November 2026 · 10 min read

Apartment tower in Bengaluru
FeatureHome Buyer Guide
Apartment tower in Bengaluru. Photo: Manoharhd · CC BY-SA 4.0, via Wikimedia Commons
The short version
  • Possession is the one moment when you still have leverage. After you sign the handover papers and take the keys, fixing problems becomes harder and slower. Inspect first, sign last.
The short version
  • Do three things in order: check the documents (completion and occupancy papers, the agreement's promises), inspect the flat room by room against the agreement, and settle the final payments only against a written list of what remains to be fixed.
The short version
  • A snag list is a dated, itemised list of defects with photographs, given to the builder in writing and signed or acknowledged. Verbal promises disappear, and written lists do not.
The short version
  • This is general guidance and not legal or technical advice. Defect and warranty terms depend on your agreement and the law, so read both, and consider hiring an inspector.

The day the builder says your flat is ready is one of the best days of the purchase and one of the riskiest. Once you sign the possession letter and take the keys, you lose most of your leverage over snags, area and papers.

This checklist is for that day and the weeks around it. It covers the papers you should receive and read, a room-by-room inspection that does not need an engineer's training, how to check the area you were sold, how to handle the final payment, and what to do when the builder says "we will fix it later." It sits between our guides on delayed possession and what you pay after possession.

Before the handover: the documents

Ask for the following in writing, before the day of inspection if you can, and check each against your agreement.

Occupancy certificate and completion papers

The occupancy certificate is the authority's statement that the building has been completed and is fit for occupation, in line with the sanctioned plan. A completion or commencement paper tells you about the stages. In many cases a lender will not complete its payments, and a flat without an occupancy certificate can bring trouble with utility connections, khata, resale and insurance. Ask for a copy, read its date and details, and check the building and the wing named in it. If the builder says it is "applied for," ask for proof and the expected date, and think hard before you take possession.

Project registration and approvals

Check that the project's registration under the real estate regulator is current and that the completion date, any extensions and any changes to the plan are recorded. Our guide to reading a K-RERA project page shows how.

The agreement and its schedules

Keep your agreement of sale, the construction agreement and the schedules of specifications and amenities open beside you. Every promise there is a checklist item: the flooring, the fittings, the doors, the kitchen and the amenities. Brochure photos do not count unless the agreement refers to them.

Statement of account and final dues

Ask for a statement of account showing what you have paid and what remains. Check each demand against the payment schedule in your agreement, not against the builder's reminder. Look for charges that appear only at possession, such as the maintenance deposit, the corpus fund, the legal charges, the infrastructure charges and the advance maintenance. See the real cost of buying and our cost sheet guide to see which ones should have been in your cost sheet from the start.

Sale deed, khata and utility

Find out how and when the sale deed will be registered, and who bears the costs. See property registration in Karnataka. Ask about the khata for the flat and the timeline for the transfer, and whether electricity and water connections are in place or are the owners' job. See E-Khata in Bangalore.

Handover letter and keys

Do not sign the possession letter until you have inspected. A possession letter often has wording that says you accept the flat in its present condition, and waives claims. Ask your advocate to read it first, and ask for it to include a reference to your snag list.

The area check

The size of the flat is in your agreement, and it is the one number you paid for. Check it.

  • Ask for the carpet area, the built-up area and the super built-up area as they are written in the agreement and the project registration.
  • Measure the carpet area of the main rooms yourself, wall to wall inside, and compare with the room dimensions in the plan. Small differences are normal in the finish, and large differences are worth a conversation.
  • Check the balcony, the utility and the terrace areas, which may be counted differently in the paperwork.
  • If the area is lower than promised, ask the builder to explain in writing. The regulator's rules and your agreement describe what happens when the area differs. Take advice before you accept.

The snag inspection, room by room

Go on a bright day, ideally in the morning, and bring a torch, a phone with a camera, a small spirit level or a bubble-level app, a plug tester, a tape, a notepad and a friend. Do not rush. Allow two or three hours, or hire an inspector (see below).

At the door and the entrance

  • The main door, frame and lock: does it open and close smoothly, and does the lock work with all the keys?
  • The nameplate and doorbell, if provided.
  • Gaps between the frame and the wall.

Walls, ceilings and floors

  • Look along walls in the light for cracks, bulges, uneven plaster and patchy paint.
  • Look at corners and edges, where cracks often begin.
  • Tap tiles gently with a coin or the handle of a key. A hollow sound can mean a poor bond. Check for cracked, chipped or uneven tiles and mismatched colour.
  • Check the skirting and the gaps between tile and wall.
  • Check ceilings for stains, which can indicate leaks from above.

Doors and windows

  • Open and close every door and window. They should move freely, latch and lock.
  • Check the glass, frames and handles for scratches, gaps and loose parts.
  • Look at the seals around windows for light or water gaps.
  • Check the balcony doors and the sliding tracks.

Electrical

  • Test every switch and socket. A plug tester shows wiring faults.
  • Check that all the lights, fans and the distribution board work, and that the trip switches are labelled.
  • Count the points and compare with the specifications.
  • Look for loose plates and exposed wires.

Plumbing and water

  • Run every tap and shower. Check pressure, hot and cold, and any leak under the sink.
  • Flush every toilet and check the cistern fills and stops.
  • Pour water on the floor of each bathroom and balcony and watch that it drains towards the outlet and does not pool.
  • Look for damp and seepage on walls adjacent to bathrooms.
  • Check that the water supply, tanks and pumps for the building are in place and described. See water checks before buying.

Kitchen and fittings

  • Check the counter, sink, taps, chimney points, gas pipeline and any promised fittings.
  • Check that cabinets, if provided, open and close properly.

Bathrooms

  • Check the fittings, the grouting, the slope of the floor and the exhaust.
  • Check that the door, lock and ventilation work.

Common areas and the building

Walk the corridors, the lifts, the stairs, the lobby, the parking and the amenities. Check:

  • The lifts work, and have the promised capacity and finish.
  • Fire exits, alarms and extinguishers are in place and unobstructed.
  • The parking slot you were allotted exists, is the right size and is marked.
  • The common finish matches the specifications. The clubhouse and pool should be ready or have a written date.
  • The generator, the water treatment and the sewage plant, if promised.
  • The road and the entry.

Photograph everything, with a date. Number each defect.

Writing the snag list

A good snag list is simple and specific. For each item write:

  1. 1The room and the spot, for example "bedroom 2, north wall, 30 cm from the window."
  2. 2What is wrong, for example "crack running from the corner to the ceiling."
  3. 3The photo number.
  4. 4Your request: repair, replace or redo.

Give it to the builder in writing, by email and by hand, and ask for an acknowledgement with a date. Ask for a timeline in which each item will be done. If the builder offers to fix things after possession, put that promise in writing in the possession letter.

The final payment

The last instalment, and any held-back amount, is the main lever you have. Pay what the agreement and the schedule require, against proper demand letters and receipts, and consider keeping a clearly stated sum in reserve against the snag list if your agreement allows it and your advocate agrees. Do not pay amounts the agreement does not provide for, and do not pay in cash. If your loan bank pays the builder directly, tell the bank in writing about open snags before it makes the final disbursement. See our home loan guide for the disbursal sequence.

After you have the keys

  • Defect liability. The real estate law gives buyers a period after possession during which the promoter must fix structural defects and other defects in workmanship at no charge, commonly cited as five years. Your agreement and the law set the exact terms, so read them and keep the dates. Report new defects in writing and keep copies.
  • Keep records. Store the agreement, the possession letter, the snag list, the photographs, the receipts and every email in one place.
  • Register the sale deed and complete the khata. Do not leave these for later.
  • Join the owners' association. Learn what is handed over from the builder and when. See after possession.
  • Insure the flat. Check the sum insured and what is covered.

Should you hire an inspector?

A trained inspector brings tools and experience: a moisture meter, a thermal check, a tester for sockets and a trained eye for cracks, waterproofing and finish. For a high-value flat or one you cannot inspect yourself, such as an NRI's, it is often worth the fee. DesiAcres' inspection and relationship manager support covers an on-site check with a written report, and our site-visit scorecard gives you a way to record what you see.

Frequently Asked Questions

Should I take possession of a flat with no occupancy certificate?

It is risky. The certificate is the authority's confirmation that the building is complete and fit to occupy, and its absence can affect utility connections, your loan, resale and insurance. Ask for proof of the application and the date, and take legal advice before taking the keys.

What should I do if I find defects at the handover?

List them in writing with photographs and give the list to the builder with a request for acknowledgement and a repair timeline. Do not sign a possession letter that says you accept the flat as it is without referring to the list, and consider holding back a clearly stated sum if your agreement and advocate allow it.

How long does the builder have to fix defects after possession?

The real estate law provides a defect liability period, commonly cited as five years for defects that appear after possession. Confirm the exact terms in your agreement and the law, and report each defect in writing as soon as you see it.

Can I check the carpet area myself?

Yes. Measure the inside of the main rooms and compare with the plan and the agreement. Small differences from finish are normal. Large ones should be raised in writing, and you can take advice on your rights if the area is short.

Want a second pair of eyes at handover?

DesiAcres can arrange an on-site inspection with a written snag report and a review of your possession papers before you sign. WhatsApp +91 79756 19031 or call +91 94296 93951, or see inspection support.

Sources
  1. DesiAcres, Builder delayed your possession (desiacres.com)
  2. Karnataka RERA (rera.karnataka.gov.in)
  3. DesiAcres, Inspection and RM support (desiacres.com)

Written by DesiAcres Editorial at DesiAcres Advisory Group, a Bengaluru buyer-side property advisory. General information, not legal or investment advice.