● LIVE · Pink Line BG Road stretch opening Oct 2026AlphaDesk area estimates · ₹/sqft · yearly trendSarjapur Road₹13,800▲14.7%HSR Layout₹15,500▲8.5%Whitefield₹11,500▲9.2%Koramangala₹18,500▲7%Bellandur₹11,200▲9.8%Jayanagar₹15,400▲7.2%Devanahalli₹6,800▲16.3%Hebbal₹12,500▲10.5%Electronic City₹7,200▲9.5%JP Nagar₹13,200▲7.8%BTM Layout₹11,800▲8.2%Marathahalli₹10,500▲8.8%Malleshwaram₹16,200▲6.8%Mahadevapura & Hoodi₹10,800▲10.4%Indiranagar₹19,500▲6.5%Bannerghatta Road₹9,500▲10%Thanisandra₹8,800▲11.5%Varthur₹8,400▲11.8%MG Road & CBD₹24,000▲6.2%Yeshwanthpur₹13,200▲9.2%Kalyan Nagar & HRBR₹12,500▲9.4%Yelahanka₹8,500▲12%● LIVE · Pink Line BG Road stretch opening Oct 2026AlphaDesk area estimates · ₹/sqft · yearly trendSarjapur Road₹13,800▲14.7%HSR Layout₹15,500▲8.5%Whitefield₹11,500▲9.2%Koramangala₹18,500▲7%Bellandur₹11,200▲9.8%Jayanagar₹15,400▲7.2%Devanahalli₹6,800▲16.3%Hebbal₹12,500▲10.5%Electronic City₹7,200▲9.5%JP Nagar₹13,200▲7.8%BTM Layout₹11,800▲8.2%Marathahalli₹10,500▲8.8%Malleshwaram₹16,200▲6.8%Mahadevapura & Hoodi₹10,800▲10.4%Indiranagar₹19,500▲6.5%Bannerghatta Road₹9,500▲10%Thanisandra₹8,800▲11.5%Varthur₹8,400▲11.8%MG Road & CBD₹24,000▲6.2%Yeshwanthpur₹13,200▲9.2%Kalyan Nagar & HRBR₹12,500▲9.4%Yelahanka₹8,500▲12%
DesiAcres Advisory GroupClarity before capitalAlphaDesk 360
← All news
Metro & infraMay 2026

Hebbal–Silk Board tunnel road: lowest bid ₹22,267 Cr, 24–28% above estimate — decision pending

The 16.7-km twin-tunnel road promises a 35-minute north–south drive. Here's why it's stuck, and what buyers along the route should (and shouldn't) assume.

AlphaDesk Research by DesiAcres Advisory Group · 6 October 2026 · 6 min read
Tunnel length
~16.7 km
Lowest bid
₹22,267 Cr
Above estimate
24–28%
Claimed trip
90 → 35 min
Photo: Traffic in Bangalore image by Anandha abirami Govindan, CC BY-SA 4.0, via Wikimedia Commons

The proposed tunnel road would connect Esteem Mall junction at Hebbal with Central Silk Board through about 16.74 km of six-lane underground twin tunnels, built as a public-private partnership with 40% viability-gap funding from the government. Its backers claim it could cut a 90-minute peak commute to around 35 minutes.

The Adani Group emerged as the lowest bidder at ₹22,267 crore, but that is 24–28% above the government's estimate, and as of May 2026 the cabinet decision on whether to accept the bid was still pending. The project has also drawn criticism — including calls from MP Tejasvi Surya for a geological impact assessment — and public campaigns questioning its cost.

The AlphaDesk take

Don't price a home on the assumption that the tunnel road will be built. Even if approved, a project of this complexity is many years away. Metro lines that are already under construction (Pink and Blue) are far more reliable reasons to choose a location.

Areas in focus — live AlphaDesk data

Try the Market Map Try the Area Matchmaker

Sources

  1. Bengaluru tunnel road: Adani lowest at ₹22,267 Cr — PropNewz
  2. Tunnel road project faces delay as government reviews costly tenders — Oneindia
  3. MP Tejasvi Surya seeks geological impact assessment of tunnel road — Deccan Herald

Figures are as reported by the sources above on or before the AlphaDesk publication date. “AlphaDesk take” sections are our analysis, not advice. Verify details before making decisions.